Guide · The fitting

How long a kitchen takes, week by week

The KÜINA team · Updated October 11, 2026

The short answer

From the first showroom visit to a finished kitchen is 8 to 14 weeks. Most of that is manufacturing: 4 to 8 weeks from the order being placed. You will be without a kitchen for considerably less, 5 to 12 working days, which is how long the building work and fitting take.

The full calendar

WhenWhat happensHow long
Week 1Showroom visit, rough measurements and a first design1 to 2 days
Week 1–2Design adjustments and a firm quote3 to 7 days
Week 2–3Technical survey at your home, with the real plan1 day
Week 3Order signed and sent to the factory—
Week 3–11Manufacture and shipping4 to 8 weeks
Week 10–11Building work: strip-out, plumbing, electrics, plastering3 to 7 days
Week 11–12Fitting the units2 to 4 days
Week 12Templating, cutting and fitting the worktop3 to 10 days between template and fit
Week 12–13Appliances, trims and snagging1 to 2 days

The wide part of the range is almost always manufacturing and the worktop, not the fitting.

Where the time actually goes

  • Deciding. Between the first visit and the signature there can be three weeks or three months. That part is in your hands.
  • Stone, porcelain or quartz worktops. They cannot be cut until the units are in, because the template is taken off them. Between template and fitting is 3 to 10 days. It is why many kitchens are used for a week without a finished worktop.
  • An unexpected find. A lead pipe, a wall that is not brick, wiring that will not take an induction hob. Add 2 to 5 days.
  • Changing something after signing. A finish change once the order is in the factory can cost the whole lead time again.

How many days without a kitchen

Type of refitDays without a kitchen
Doors and worktop only2 to 3 days
New kitchen, same layout5 to 8 days
New kitchen, moving the sink or hob8 to 12 days
New kitchen, taking out a partition wall12 to 20 days

It can almost always be shortened by keeping the fridge and microwave out of the work area and leaving the appliances until the last day.

What you can do to stop it dragging

  1. Finalise the design before asking for the final price. Every change restarts the clock.
  2. If you are supplying your own appliances, have them bought and measured before the technical survey.
  3. Ask the building management for permission if works notice is required: in some buildings that is a week of lead time.
  4. Decide the tile or panel colour before the work starts, not during it.
  5. Be reachable during fitting week. Half of all one-day delays are an unanswered phone call.

Questions we get asked

Can a kitchen be done in a month?

Only if the units come from a stocked range and the worktop is laminate, which can be cut the same day. With made-to-order units and a stone or porcelain worktop, no.

Can I live at home during the work?

Yes, in most cases. The awkward part is the two or three dusty days of strip-out and chasing. The practical answer is a temporary corner with a fridge, a microwave and a kettle in another room.

Why is it measured twice?

The first measurement is for designing and quoting. The technical survey happens with the old kitchen still in or already out, and it is what goes to the factory: that is where out-of-true walls, real ceiling heights and the position of services show up.

What if the factory runs late?

It happens. What you should insist on is being told as soon as it is known, not during fitting week, and that the fitting date is rescheduled in days, not hours.

Shall we look at it with your kitchen on screen?